Project Update

ACME Solar Holdings Limited (ASHL), through its wholly owned subsidiary ACME Sigma Urja Private Limited, has commissioned additional discharge capacity of 14.55 MW/60.387 MWh (installed capacity: 14.55 MW/65.195 MWh) at the TATA FDRE Power Project. This is part of the larger 50 MW/209 MWh (installed capacity: 50 MW/220 MWh) project.

Project Location

The project is located at Village: Neemri, Tehsil: Rawatbhata, District: Chittorgarh, Rajasthan.

Key Dates

The additional capacity was commissioned on November 24, 2026. The Commercial Operation Date (COD) for this capacity is scheduled for November 26, 2026.

Contractual Arrangements

The Power Purchase Agreement (PPA) for this project has been signed with The Tata Power Company Limited.

Cumulative Capacity Achievement

With this commissioning, ACME Sigma Urja Private Limited has achieved a cumulative commissioned BESS discharge capacity of 50.36 MW/209.032 MWh (installed capacity: 50.36 MW/225.675 MWh).