ACME Solar Holdings Limited, through its subsidiary ACME Renewtech Private Limited, has commissioned an additional 66.68 MW of solar power capacity at its hybrid project in Bikaner, Rajasthan. This latest operational milestone increases the hybrid project's total operational capacity to 200.04 MW.
The Commercial Operation Date (COD) for this additional capacity is specified as November 04, 2026. The company plans to add wind capacity to this hybrid project to complement solar generation, enabling a more diversified renewable energy generation profile.
Following this commissioning, ACME Solar's total operational capacity now stands at approximately 3,190 MW. The project is located at Kelan Village in Bikaner, Rajasthan, and has a Power Purchase Agreement (PPA) signed with NTPC Limited at a tariff of ₹3.36 per kWh.
ACME Solar expects to progressively operationalize the entire 300 MW solar component of this project by the end of Q3 FY27. The company describes itself as a leading integrated renewable energy player with a diversified contracted portfolio of 8,370 MW spanning solar, wind, storage, FDRE and hybrid solutions, along with 5.64 GWh of BESS capacity.
The disclosure note specifies that this is a voluntary submission and not to be considered as an intimation under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.