Project Commissioning Details
ACME Solar Holdings Limited, through its subsidiary ACME Renewtech Private Limited, has commissioned an additional 66.68 MW of the solar component of its Hybrid Power Project. The commissioning occurred on November 02, 2026. The project is located at Village-Kelan, Tehsil-Chhatargarh, District-Bikaner, Rajasthan.
Commercial Operation Date
The Commercial Operation Date (COD) for this newly commissioned capacity is set for November 04, 2026.
Cumulative Capacity Achievement
With this additional commissioning, ACME Renewtech Private Limited has achieved a cumulative commissioned solar capacity of 200.04 MW out of the total 300 MW Hybrid Power Project capacity.
Power Purchase Agreement
The project operates under a Power Purchase Agreement (PPA) that has been signed with NTPC Limited.