Date: October 14, 2026
Board Meeting Outcomes
The Board of Directors of Aeroflex Industries Limited met on October 14, 2026 (10:30 AM to 11:04 AM) and made the following decisions regarding capacity enhancements and expansion plans:
Capacity Enhancement Status
SS Hose & Braiding Division:
- Successfully completed capacity enhancement to 20 million meters per annum
- Current capacity utilization: 70% (as of quarter ended June 30, 2026)
Liquid Cooling SFN Skid Assemblies Division:
- Successfully completed capacity enhancement to 12,000 pieces per annum
- Remaining 3,000 pieces capacity (to reach 15,000 pieces total) expected by December 2026
- Current capacity utilization: 69% (as of quarter ended June 30, 2026)
Approved Expansion Plans
SS Hose & Braiding Division Expansion:
- Capacity enhancement from 20 million to 30 million meters per annum (10 million meters increase)
- Setting up new State of the Art Assemblies Plant to convert 70%-75% of hoses and braids into assemblies
- Estimated investment: ₹124 crores
- Expected completion: Phased manner by March 2028
Liquid Cooling SFN Skid Assemblies Division Expansion:
- Capacity enhancement from 15,000 to 30,000 pieces per annum (15,000 pieces increase)
- Setting up additional facility
- Estimated investment: ₹78 crores
- Expected completion: Phased manner by March 2028
Financial Arrangements
- Total aggregate investment: ₹202 crores
- Financing mode: Internal Accruals, Equity and Bridge Loan Financing
Rationale
Both expansion projects are intended "To meet the future demands" as stated in the regulatory disclosure.