Key Quantitative Figures

The company has successfully commissioned a ground-mounted solar power plant with capacity of 2.4 MWp (DC)/1.75 MWp (AC).

Dates of Action

The solar power generation commenced effective from April 24, 2026. The Certificate of Commissioning was received from Gujarat Energy Development Agency (GEDA) on May 12, 2026. The disclosure was made to the exchange on June 20, 2026.

Parties Involved

  • Aksharchem (India) Limited (Company)
  • Gujarat Energy Development Agency (GEDA) (Certifying authority)

Location Details

The solar power plant is located at Village: Sardarpura, Ta: Jhagadiya, Dist. Bharuch. The power is for captive consumption at the company's factory located at Dahej, Gujarat.

Purpose and Rationale

The development reflects the company's ongoing efforts to enhance its renewable energy portfolio and contribute to sustainable power generation initiatives.