Nature of Update
Timeline extension for completion of second tranche investment in MoMagic Wireless Private Limited by IL JIN Electronics (India) Limited, a material subsidiary of Amber Enterprises India Limited.
Original vs Revised Timeline
- Original completion deadline: On or before 30th September 2026 (or such other date as mutually agreed)
- Revised completion deadline: On or before 30th November 2026 (or such other date as mutually agreed)
Current Status of Acquisition/Project
The second tranche of investment through acquisition of additional equity stake in MoMagic Wireless Private Limited remains pending completion.
Additional Information
- This intimation is available on Company's website at www.ambergroupindia.com
- Company commits to make requisite disclosures and provide further updates in due course
- Signed by Konica Yaadav, Company Secretary and Compliance Officer (M. No. A30322)