Date: August 14, 2026

Operational Update

Manufacturing Operations Restoration:

  • The third paper machine at the Company's Kadiam Unit has resumed operations effective August 14, 2026
  • This machine has a production capacity of 15 MT per day
  • With this commencement, the operational capacity at the Kadiam Unit stands fully restored to 100% of its normal production capacity
  • This represents an improvement from the previously reported 93% capacity level

Disruption Background:

  • The disclosure is in continuation of earlier disclosures dated July 15, 2026 and July 23, 2026 regarding resumption of manufacturing operations
  • The disruption occurred at the Kadiam Unit, East Godavari, Andhra Pradesh — 533126
  • The disruption was attributable to demands raised by contract workmen regarding revision of certain contractual terms

Financial Impact Assessment:

  • No quantum of loss/damage caused — None reported
  • Not applicable for insurance coverage as there was no physical damage to assets
  • All insurable assets are adequately covered by insurance
  • Manufacturing operations have fully restored to 100% of normal production capacity

Not Specified Sections

No material disclosures under the following sections: Financial Results, Dividend Declaration, KMP/Board/Auditor Changes, Board Meeting Outcomes, Auditor's Report, Disinvestment/Strategic Actions, Media Release/Investor Communication, Other Operational/Legal/Strategic Disclosures.