  • Manufacturing operations at the Kadiam Unit have partially commenced effective July 15, 2026
  • One paper machine with production capacity of 150 MT per day has resumed operations
  • This represents approximately 70% of the total production capacity of the Kadiam Unit
  • The situation is expected to further improve leading to resumption of full operations
  • Full resumption is subject to increase in attendance of support manpower and progressive stabilisation of operations

Labor Situation

  • Permanent employees have resumed duties in their respective shift schedules
  • Attendance of contract workmen engaged through third-party manpower contractors remains below normal levels
  • Current contract workmen attendance is around 35% of the normal strength
  • The disruption was attributable to demands raised by contract workmen regarding revision of certain contractual terms
  • The Company made all necessary arrangements for resumption post revocation of lockout (as previously disclosed on 30.04.2026, 02.05.2026, 30.05.2026 and 04.06.2026)

Unit Details

  • Factory/Unit: Kadiam Unit
  • Location: East Godavari, Andhra Pradesh - 533126

Financial Impact Assessment

  • Expected quantum of loss/damage caused: None
  • Loss/damage covered by insurance: Not applicable (no physical damage to assets)
  • All insurable assets are adequately covered
  • Supporting activities continue to experience operational constraints due to limited availability of contract workmen