Key Events and Details
Shareholder Complaint
- The company received an email dated 23rd November, 2026 from Mr. Mahendra Kumar, a shareholder (DP ID: 12081601, BO Client ID: 87604577, holding 13,500 shares)
- The representation was addressed to SEBI, NSE, BSE, and ROC regarding cancellation of the EGM scheduled on 23rd November, 2026
- Primary allegations include:
- Lack of statutory quorum (only 20 persons present vs mandatory 30 members required under Section 103 of Companies Act, 2013)
- Failure to provide e-voting facility to approximately 35,000 public shareholders
- Violation of SEBI LODR Regulations, specifically Regulations 4 and 44
- Illegal voting by show of hands instead of electronic voting
- Violation of NCDRC orders dated 29th April 2026 and 4th November 2026 that stay any change in management and control
Company's Previous Communication
- The company had already intimated stock exchanges on 18th November 2026 about not proceeding with the requisition letter dated 27th October 2026
- The requisition was from certain shareholders belonging to the Promoter and Promoter Group seeking to convene an EGM on 23rd November 2026
- Reasons cited: The requisition suffers from various material deficiencies and non-compliances with provisions of Companies Act, 2013 and Listing Regulations
Newspaper Reports
- The company has come across various newspaper publications with headline "Ansal API Promoters' proposed EGM collapses amid quorum shortfall and alleged statutory violations"
- Reports confirm the EGM scheduled at 1:00 p.m. at Roseate House Hotel, Aerocity, New Delhi failed to muster the mandatory 30-member quorum
- Public shareholders resisted due to absence of mandatory e-voting facility
Legal and Insolvency Context
- Vide Orders of Hon'ble Supreme Court dated 16th April 2026 and Hon'ble NCLAT dated 7th January 2026
- Corporate Insolvency Resolution Process (CIRP) under IBC 2016 is confined to Lucknow and Rajasthan projects only
- As per NCLT Order dated 19th November 2026:
- Shri Navneet Kumar Gupta continues as Resolution Professional for Rajasthan projects
- Shri Surendra Raj Gang appointed as Resolution Professional for Uttar Pradesh projects
Shareholder Demands
Mr. Mahendra Kumar requested regulatory authorities to:
- Initiate immediate inquiry into the illegal conduct of the purported EGM
- Declare the EGM automatically cancelled under Section 103(2)(b) of Companies Act, 2013
- Issue interim directions restraining promoters from taking any action based on the EGM
- Direct ROC not to accept any statutory filings arising from the invalid EGM
- Initiate regulatory proceedings against promoters for violations
Attachments
- Annexure-A: Complete shareholder representation email with video evidence