Key Quantitative Figures
- Penalty amount: ₹2,07,867 (Rupees Two Lakh Seven Thousand Eight Hundred and Sixty-Seven Only)
- Base extension fee amount: ₹1,38,578
- Calculation methodology: 10% of extension fee per month of delay
- Duration of delay: 15 months
Parties Involved
- Issuing authority: Haryana Real Estate Regulatory Authority (HRERA)
- Project involved: "Ansal Town Yamunanagar DDJAY-SCH-1"
- Compliance Officer: Shalini Talwar
Details of Violation
Delay in payment of extension fee for the project "Ansal Town Yamunanagar DDJAY-SCH-1" as specified in the HRERA order.
Financial Impact Assessment
The order entails a financial liability of ₹2,07,867 towards the penalty imposed. The company explicitly states there is no material impact on the financials, operations, or other activities of the company due to this order.
Disclosure Reference
Ref No.: SECY/S-16/2026 dated 23rd October 2026
#Tags: #AnsalHousing #HRERA #SEBIDisclosure #RegulatoryCompliance #Penalty #Neutral