Core Announcement – Order Details
Awarding Entity: Adani Power Limited
Domestic/International Order: Domestic entity
Nature of Order/Contract:
Supply of equipment (Boiler, Turbine and Generator along with auxiliaries) and Agreed Services for 4 projects of 2x800 MW each. The contracts represent major thermal power plant equipment supply agreements.
Order Value:
4 projects (contracts) each valued at Rs. 5,000 – 7,000 Cr. excluding GST. Total aggregate value range: ₹20,000 – ₹28,000 crore excluding GST.
Materiality Context:
Not Specified
Execution Timeline:
As per Customer's Project requirements. No specific completion deadline or timeline disclosed.
Revenue Recognition / Billing Structure:
Not Specified
Key Terms & Payment Milestones:
Not Specified
Whether Related Party Transaction:
No
Promoter Group Involvement:
No
Financial Implication:
Not Specified