Project Details and Revised Timeline

The disclosure concerns the 9.9 MW Hybrid Power Project located at Kalikanagar, Gujarat. This filing is a continuation of a previous intimation dated November 2, 2026, which also reported a delay.

Based on a communication dated November 27, 2026, received from the project developer, Clean Max Enviro Energy Solutions Limited, the commissioning schedule has been further revised. The new tentative timeline is as follows:

  • The first Wind Turbine Generator (WTG) location along with the 7.65 MW solar component is expected to be commissioned before December 31, 2026.
  • The second WTG location is expected to be commissioned by December 31, 2026.
  • The third WTG location is expected to be commissioned by March 31, 2027.

The project was previously expected to be commissioned by October 31, 2026.

Reason for Delay

The reason for the further delay, as stated by Clean Max Enviro Energy Solutions Limited, is attributed to factors outside their control. The primary cause is the inability of a nearby industry hub to secure a timely shutdown of the existing 33 KV and 11 KV power lines. This shutdown is required from both a private developer and the state utilities, GETCO/PGVCL, to facilitate 33KV transmission line (TL) work. This obstacle has prevented the project from achieving its original commissioning date.

Attachments and Signatories

The filing includes an attached update letter from Clean Max Enviro Energy Solutions Limited, dated November 27, 2026. The letter to the exchanges was signed digitally by Ankur Mangilal Borana, Executive Director and Chief Executive Officer of Borana Weaves Limited (DIN: 01091164). The attached letter from Clean Max was signed by Mayur Purushottam Bhagat, Project Executive.

Financial Impact

Financial impact not quantified in the disclosure.