Date: June 18, 2026

Operational / Strategic Disclosures

Borana Weaves Limited received a communication dated June 18, 2026, from its project developer, Clean Max Enviro Energy Solutions Limited, regarding a revision in the commissioning timeline for its 9.9 MW Hybrid Power Project.

The project is being developed at Kalikanagar, Gujarat.

The original commissioning date was expected by May 31, 2026.

The revised, tentative commissioning date is now the end of August 2026.

The reasons cited for the delay are external factors outside the developer's control:

  • High wind speeds that halted Wind Turbine Generator (WTG) erection work.
  • A shortage of fuel at the project site.
  • An inability to get a timely shutdown of existing 33 KV and 11 KV lines from a private developer and GETCO/PGVCL, which prevented the completion of 33KV Transmission Line (TL) work.