Date: 29-08-2026

Project Update

Borana Weaves Limited provided an update on the commissioning delay of its 9.9 MW Hybrid Power Project at Kalikanagar, Gujarat. This disclosure is made pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, and continues from the company's earlier intimation dated June 18, 2026.

Revised Commissioning Timeline

The project commissioning has been revised with the following tentative schedule:

  • One WTG location along with the 7.65 MW solar component is expected to be commissioned by September 30, 2026
  • The remaining two WTG locations are expected to be commissioned by the end of October 2026

Reasons for Delay

The delay is attributed to factors beyond the project developer's control:

  • High wind speeds affecting WTG erection operations
  • Heavy monsoon conditions requiring additional logistics-road rework
  • Delay in obtaining shutdowns of existing 33 kV and 11 kV lines from private developer and GETCO/PGVCL for 33 kV transmission-line work

Project Developer Communication

The announcement includes communication from Clean Max Enviro Energy Solutions Limited (project developer) confirming the revised timeline and reasons for delay. The project was originally expected to be commissioned by August 31, 2026.