Date: 13.10.2026

Board Meeting Outcomes

  • Received Completion Certificate from Authority's Engineer dated 12th October 2026 for Delhi-Saharanpur Highway project
  • Certificate issued pursuant to Article 12 of EPC Contract Agreement
  • Project declared fit for entry into operation effective from 12th September 2024

Project Details

Completed Project:

  • Project Name: Development of six-lane access controlled highway in Uttar Pradesh portion of Delhi-Saharanpur Highway from Delhi/UP Border to EPE Junction (Ch. 14.750 to 31.600)
  • Location: Uttar Pradesh
  • Project Type: Economic Corridor under Phase-1 of Bharatmala Pariyojna
  • National Highway No.: NH-709B
  • Estimated Project Cost: ₹1,659.84 crore
  • Award Date: April 16, 2022
  • Original Scheduled Completion: November 7, 2023
  • Extended Completion Date: August 15, 2024 (EOT approved)
  • Cure Period: 30 days from approved EOT
  • Actual Operational Date: September 12, 2024
  • Project Term: 910 days
  • Authority: National Highways Authority of India (NHAI)
  • Contract Model: EPC (Engineering, Procurement, Construction)
  • EPC Value: ₹1,323.52 crore

Special Conditions:

  • Completion certificate issued except for works included in settlement agreement between Gayatri Projects Limited & Ceigall India Limited and NHAI dated October 9, 2026

Ongoing Projects Disclosure

The company provided details of five ongoing projects:

1. Bihta-Koilwar Section, Bihar

  • Description: Existing two lane carriageway to four lane carriageway from Design Ch:19+870 to Design Ch:23+500
  • Total Length: 25.081 km
  • State: Bihar
  • Mode: EPC (2nd call)

2. Delhi-Saharanpur Highway, Uttar Pradesh (Recently Completed)

  • Bid Project Cost: ₹13,235.20 lakh
  • Award Date: April 16, 2022
  • Estimated Completion: November 7, 2023
  • Term: 910 days
  • Authority: NHAI

3. Amritsar Connectivity, Punjab

  • Description: Construction of four-lane Greenfield Amritsar connectivity connecting Amritsar with Delhi-Amritsar-Katra Expressway
  • Location: From MDR Junction at ch. 40+900 Dhunda Village to Junction with NH3 and Taran taran Bypass near Mannawalla village chainage 70+950
  • Length: km 40+900 to km 70+950
  • Bid Project Cost: ₹10,710.00 lakh
  • Award Date: May 12, 2021
  • Status: Appointed date not declared yet
  • Term: 730 days
  • Authority: NHAI
  • Program: Bharatmala Pariyojna

4. Ludhiana Rupnagar National Highway, Punjab

  • Description: Construction Of Four/Six Lane Greenfield NH-205K from Junction With NE-5 Village near Manewal to junction with NH-205 near Bheora Village including spur to Kharar with Ludhiana bypass
  • Design Ch.: 66.440 to 90.500 and spur to Kharar Design Ch. 0.000 To 19.200
  • Total Length: 43.26 km
  • Bid Project Cost: ₹10,382.40 lakh
  • Award Date: June 2, 2022
  • Estimated Completion: February 15, 2025
  • Term: 730 days
  • Authority: IRCON
  • Program: Bharatmala Pariyojana

5. Delhi-Amritsar-Katra Expressway, Punjab

  • Description: Construction of four-lane Greenfield Delhi-Amritsar-Katra Expressway from Junction with Patiala-Bathinda road (NH-7) near Bhawanigarh to Junction with Ludhiana-Malerkotla road (SH-11) near Bhogiwal village
  • Bid Project Cost: ₹8,810.00 lakh
  • Award Date: July 20, 2021
  • Estimated Completion: July 10, 2024
  • Term: 730 days
  • Authority: NHAI