Project Details
Deshraj Solar Energy Private Limited, a step-down subsidiary of CESC Limited, has declared the Commercial Operation Date (COD) for 147 MW out of its 150 MW Solar Power Project.
Project Location and Specifications
The project is located at Village Karnisar Bhatiyan, District Bikaner, Rajasthan, and is connected at ISTS Bikaner-III (PGCIL) substation.
Commercial Operation Date
The COD was declared effective from November 21, 2026.
Certification and Approval
The commercial operation follows successful trial run certified by Grid Controller of India Limited (Northern Regional Load Despatch Centre) via certificate dated November 19, 2026.
Remaining Capacity
The balance capacity of 3 MW is expected to be commissioned by January 31, 2027.