Disclosure under Regulation 30 of SEBI LODR Regulations

Timeline Revision Details

Pursuant to the second amendment to the Share Purchase Agreement, the indicative timeline for completion of the acquisition has been revised from November 21, 2026 to December 15, 2026. This follows an earlier revision from October 31, 2026 to November 21, 2026 communicated via letter dated October 31, 2026.

Acquisition Background

The acquisition was initially announced on August 10, 2026, when Purvah Green Power Private Limited (PGPPL), a subsidiary of CESC Limited, entered into a Share Purchase Agreement with ReNew Solar Power Private Limited (Seller) for acquisition of 100% share capital of six target companies.

Target Companies and Capacity Details

The acquisition involves six renewable energy companies with total installed capacity of approximately 1.4 GWp (1,411.48 MW):

  • ReNew Hans Urja Private Limited: 810 MWp
  • ReNew Solar Photovoltaic Private Limited: 506.25 MWp
  • ReNew Wind Energy (Karnataka 3) Private Limited: 24.55 MWp
  • ReNew Wind Energy (MP Four) Private Limited: 24.60 MWp
  • ReNew Wind Energy (Karnataka 4) Private Limited: 22.90 MWp
  • ReNew Agni Power Private Limited: 23.18 MWp

Financial Considerations

Enterprise Value: ₹4,859 crores (excluding contingent payment of estimated ₹230 crores payable only on additional realization of change in law claim)

Cash Consideration on Closing: ₹1,582 crores (including ₹94 crores of net current assets but excluding contingent payment amount), comprising:

  • Payment to sellers for share capital: ₹589 crores
  • Infusion of unsecured promoter debt: ₹993 crores (to be used for repayment of existing promoter debt)

The consideration is subject to post-closing adjustments as set out in the Share Purchase Agreement.

Individual Company Acquisition Costs

  • ReNew Hans Urja Private Limited: ₹137.9 crores
  • ReNew Solar Photovoltaic Private Limited: ₹118.4 crores
  • ReNew Wind Energy (Karnataka 3) Private Limited: ₹79.2 crores
  • ReNew Wind Energy (MP Four) Private Limited: ₹71.1 crores
  • ReNew Wind Energy (Karnataka 4) Private Limited: ₹86.7 crores
  • ReNew Agni Power Private Limited: ₹95.5 crores

Strategic Impact and Rationale

The transaction will expand CESC's renewable power footprint. Post-acquisition, the company's operational capacity will increase to over 1.8 GWp and contracted/tied-up capacity will reach over 3 GWp (totaling 4.8 GWp). This significantly accelerates the company's pan-India presence.

Regulatory and Compliance Aspects

  • The acquisition does not fall within related party transactions
  • No promoter/promoter group/group companies of CESC have any interest in the target companies
  • No governmental or regulatory approvals are required for the acquisition

Target Company Background

Detailed financial and operational information for each target company:

ReNew Hans Urja Private Limited

  • Incorporated: June 8, 2021
  • Business: Generation and supply of power from renewable sources
  • Commissioned in parts between July 28, 2024 and December 23, 2024
  • Turnover: FY24-25: ₹132.8 crores, FY23-24: ₹0.1 crores

ReNew Solar Photovoltaic Private Limited

  • Incorporated: September 13, 2021
  • Business: Generation and supply of power from renewable sources
  • Commissioned: March 25, 2025
  • Turnover: FY24-25: ₹41.5 crores, FY23-24: ₹0.0 crores

ReNew Wind Energy (Karnataka 3) Private Limited

  • Incorporated: June 1, 2013
  • Business: Generation and supply of power from renewable sources
  • Commissioned: March 27, 2017
  • Turnover: FY24-25: ₹19.0 crores, FY23-24: ₹20.6 crores, FY22-23: ₹19.6 crores

ReNew Wind Energy (MP Four) Private Limited

  • Incorporated: March 5, 2015
  • Business: Generation and supply of power from renewable sources
  • Commissioned: April 28, 2017
  • Turnover: FY24-25: ₹19.5 crores, FY23-24: ₹20.3 crores, FY22-23: ₹19.8 crores

ReNew Wind Energy (Karnataka 4) Private Limited

  • Incorporated: November 23, 2013
  • Business: Generation and supply of power from renewable sources
  • Commissioned: March 31, 2017
  • Turnover: FY24-25: ₹20.1 crores, FY23-24: ₹23.7 crores, FY22-23: ₹21.1 crores

ReNew Agni Power Private Limited

  • Incorporated: October 6, 2015
  • Business: Generation and supply of power from renewable sources
  • Commissioned: March 31, 2017
  • Turnover: FY24-25: ₹20.6 crores, FY23-24: ₹24.6 crores, FY22-23: ₹21.0 crores

All target companies are incorporated in India and engaged in renewable power generation and project development.

Press Release Highlights

The press release dated August 10, 2026, describes this as one of the largest acquisitions of operating solar assets in the Indian market. More than 90% of the capacity is contracted with SECI under 25-year power purchase agreements, with the balance contracted with Karnataka distribution companies.

Corporate Structure Impact

Post-acquisition completion, the target companies will become step-down subsidiaries of CESC Limited.

#CESC #RenewableEnergyAcquisition #SEBIDisclosure #RegulatoryCompliance #M&A