Key Quantitative Figures

  • Total order value: ₹21,424,092.20 (Rupees Twenty One Millions Four Hundred Twenty Four Thousand and Ninety Two Only)
  • Amount includes GST

Parties Involved

  • Desco Infratech Limited (recipient)
  • KP Energy Limited (awarding entity)
  • Adani Total Gas Limited (awarding entity)
  • Maharashtra Natural Gas Limited (awarding entity)

Order Details

Client 1: KP Energy Limited

Nature of Work: Supply & installation works, including HDPE pipe supply, cable laying with digging, OFC cable laying and associated electrical/underground works for KPI-GUVNL Solar Project – Phase II

Client 2: Adani Total Gas Limited

Nature of Work: Execution of MDPE Pipeline and Last Mile Connectivity (LMC) works at Mahendragarh, Haryana

Client 3: Maharashtra Natural Gas Limited

Nature of Work: Laying of underground PE pipeline and aboveground GI/Cu installation for CGD Network of MNGL for Nizamabad GA

Contract Terms

  • Significant terms and conditions: As per the Contract
  • Entity type: Domestic entities
  • Time period for execution: As per the Contract

Related Party Disclosure

  • Promoter/promoter group/group companies have no interest in the entities that awarded the orders
  • The orders do not fall within related party transactions (NA)