Diamond Power Infrastructure Limited has received a Letter of Intent (LOI) from Aurionpro Solutions Limited for the supply of HT and LT electrical cables to a hyperscale data centre campus at Hyderabad. The disclosure is made pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.

Order Details

  • Order Value: ₹52.86 crore (including GST)
  • Client: Aurionpro Solutions Limited (NSE: AURIONPRO | BSE: 532668)
  • Project: HYD-20 package of a hyperscale data centre campus at Hyderabad
  • Nature: Supply of HT and LT electrical cables
  • Entity Type: Domestic
  • Execution Timeline: Supplies commence immediately and are scheduled on a staggered basis in line with the site's construction programme
  • Delivery Terms: Delivered DAP Hyderabad
  • Pricing Mechanism: Price-variation basis under the IEEMA formula with April 2026 base indices

Technical Specifications

The order comprises approximately 130 kilometres of cable with the following breakdown:

  • Over 116 kilometres of 1100 V grade, XLPE-insulated, FRLS-sheathed 1C x 300 sq mm copper conductor cable (backbone distribution cable for high-density server halls)
  • Balance includes 33 kV (E) grade aluminium XLPE armoured FRLS cable, 1.1 kV aluminium armoured LT power cables, and copper control cables
  • All cables built to the client's IEC 61914 cleat and fire-performance specifications

Business Context

The order is overwhelmingly copper-intensive and utilizes the company's recently commissioned copper wire drawing and copper cable manufacturing line, which has a capacity of 1,500 MT of copper cables per month. This marks the company's entry into copper-based cables alongside its established aluminium cables and conductors business.

Relationship Disclosure

The order has been received in the ordinary course of business and at arm's length. The promoter/promoter group/group companies do not have any interest in Aurionpro Solutions Limited. The transaction does not fall within related party transactions.

Management Commentary

Mr. Umesh Chayya, Whole time Director, stated that data centres are the single fastest-growing load centre in India and demand cable quality that few plants in the country can deliver at scale. He mentioned that the company is supplying into this campus through more than one EPC partner and intends to be the reference cable supplier for India's data centre build-out. The company's current order book for data centers exceeds ₹575 crore, and they expect to target this segment aggressively.

Additional Information

The intimation is available on the company's website at www.dicabs.com. The disclosure includes Annexure A (detailed disclosure under Regulation 30) and Annexure B (press release).