Date: October 07, 2026

Project Completion Disclosure

Dilip Buildcon Limited has received Provisional Completion Certificate for the following project:

Project Details:

  • Project: 4-Laning of Karimnagar-Warangal Section of NH-563 from Design Ch.48.860 km (near SH-1 Ch. 170.400 km) at Manakondur bypass to Design Ch.116.875 km (existing Ch.144.050 km of NH-163) at Palvelpula near Hanamkonda, (Design Length 68.015 km) in the State of Telangana
  • Project Cost: ₹1,647.00 crore
  • Mode: Hybrid Annuity
  • Project Implementation: Under Bharatmala Pariyojana
  • Appointed Date: July 18, 2023
  • Scheduled Completion Period: 730 days from Appointed Date
  • Scheduled Completion Date including EOT: September 7, 2026
  • Provisional Completion Date: September 7, 2026

Insider Trading Window Status

The trading window for dealing in the company's securities is closed for all insiders, designated persons, their immediate relatives, connected persons, fiduciaries and intermediaries from the end of the quarter until 48 hours after the declaration of financial results for the quarter ended September 30, 2026. This is in accordance with the company's Code of Conduct for Prevention of Insider Trading and SEBI (Prohibition of Insider Trading) Regulations, 2015.