Elin Electronics Limited has successfully commenced commercial production at its Bhiwadi Plant located at C-2, C-3 & C5-C6 Elcina Manufacturing Cluster Spl-1, Salarpur Industrial Area, Bhiwadi, District: Alwar, Rajasthan-301019, effective September 14, 2026.

Capacity Details

Existing Annual Capacity:

  • OFR: 80,000 units
  • Ceiling Fan: 375,000 units
  • Chimney: 72,000 units

Current Capacity Utilization (Financial Year Plan):

  • OFR: 60,000 units
  • Ceiling Fan: 350,000 units
  • Chimney: 10,000 units

Proposed Capacity Addition:

  • OFR: 125,000 units
  • Ceiling Fan: 450,000 units
  • Chimney: 240,000 units

Implementation Timeline

The proposed capacity addition is scheduled to be completed in Q2 FY26-27.

Financial Details

Investment Required: ₹5,00,00,000 (Five Crore Rupees)

Mode of Financing: Internal Accruals

Rationale

The capacity expansion is intended to cater to the enhanced requirements of the company's customers.