Nature of the Event

Enviro Infra Engineers Limited has received a Letter of Acceptance (LOA) for the execution of a sewage treatment plant project, disclosed pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.

Key Quantitative Figures

The contract has a broad consideration of ₹126.78 Crores (excluding GST).

Dates of Action

The Letter of Acceptance is dated 01.07.2026. The Company received the LOA from the concerned department on 03.07.2026. The disclosure was made to the stock exchanges on 03.07.2026.

Parties or Entities Involved

The contract was awarded by Uttar Pradesh Jal Nigam (Rural). The project will be executed through the Special Purpose Vehicle (SPV) - Varanasi DDU Nagar STP Private Limited, which was incorporated by the Company and intimated to the stock exchange on 17.06.2026.

Significant Terms and Conditions

The project involves the development of a 45 MLD Sewage Treatment Plant and Associated Infrastructure for Pt. Deen Dayal Upadhyay Nagar (DDU Nagar), State of Uttar Pradesh. It will be executed on a Hybrid Annuity Model (HAM) basis along with Operation & Maintenance (O&M) under the Namami Gange Programme.

Time Period for Execution

The construction period is 18 months, followed by 3 months for trial operations. This will be followed by an Operation and Maintenance (O&M) period of 15 years.