GAIL's Board approved extension of Kochi-Koottanad-Bengaluru-Mangaluru pipeline project completion to September 2026.
Project involves 1104 km authorized length with 919 km laid and 657 km commissioned to date.
Delay attributed to hindrance-free front availability issues as per regulatory filing.
Disclosure made under SEBI LODR Regulation 30 following Board meeting on April 13, 2026.