Project Status Update

Land Conversion & Site Preparation:

  • Conversion of land use from agricultural to industrial has been successfully completed.
  • Land filling work has been completed.

Regulatory Approvals Obtained:

  • No Objection Certificate/Consent to Establish (CTE) obtained from the West Bengal Pollution Control Board.
  • Fire NOC/Fire Safety Report (FSR) received from the West Bengal Fire & Emergency Services.
  • WBSEDCL electricity final sanction letter for sanction of power has been received. Agreement for electricity is being executed.
  • Building Plan sanction has been received from Zila Parishad.
  • With these, all regulatory approvals are in place to execute implementation of the project.

Construction & Design Progress:

  • Contract for the Pre-Engineered Building (PEB) structure has been awarded and erection work has commenced.
  • Piling work has been completed.
  • Foundation work will most likely be completed by end of October 2026.

Procurement Status:

  • Orders for all plant and machinery have been placed.
  • Order for utility equipment has been placed.

Timeline Revision

As disclosed in the Company's Red Herring Prospectus, commercial production was originally expected to commence by Q4 of FY 2025–26, which was later extended to Q3 of FY 2026–27.

The commencement of commercial production has been further extended and is now expected to commence by Q4 of FY 2026–27 due to:

1. Significant delay in building plan approval caused by SIR and elections in West Bengal, with final sanction received in July 2026 due to non-functioning of Zila Parishad

2. Excessive rain delaying piling and foundation work post receipt of Building Plan approval

3. Delay in sanctioning of power to the project due to SIR and election process

All these factors were beyond the control of the company.

Utilization of IPO Proceeds

The Company has fully utilized the proceeds raised through its Initial Public Offering (IPO) in accordance with the objects and purposes specified in the Prospectus. The utilization of IPO proceeds is in line with the commitments made to investors, and no unutilized IPO proceeds remain as on date.