To: BSE Limited and National Stock Exchange of India Limited
Key Development
The Company received a letter dated 18th September 2026 from National Highways Authority of India (NHAI) declaring the Appointed Date as 7th September 2026 for the Agra-Gwalior Greenfield Road project.
Project Details
Project Name: Construction of Agra-Gwalior Greenfield Road comprising:
- Section-1: Development of 6 Lane access controlled Agra-Gwalior greenfield highway, starting from design km 0+000 (near village Deori in district Agra) to design km 88+400 (near village Susera in district Gwalior) in the States of Uttar Pradesh, Rajasthan and Madhya Pradesh
- Section-2: Overlay/Strengthening, other road safety and improvement works on existing Agra-Gwalior section from 1058.00 to 1148.00 (Design chainage 13.00 to 103.00) of NH-44 in the States of Uttar Pradesh, Rajasthan and Madhya Pradesh
Project Specifications:
- NHAI Estimated Project Cost (Inclusive of GST): ₹4,262.78 Crores
- Mode: DBFOT pattern at BOT (Toll) Mode under NH(O) scheme
- Completion Period: 910 days from Appointed Date
- Appointed Date: 07.09.2026