Case name: Sukanti & Anr. vs Green India Infra Projects Ltd. & Ors.
Petition: Special Leave Petition (Civil) Diary No. 30193/2026.
Court: Supreme Court of India.
Related impugned judgment: Final judgment dated 16‑02‑2024 in MAC No. 1276/2015 of High Court of Chhattisgarh, Bilaspur.
Hearing date: 25‑05‑2026.
Application: IA No. 157072/2026 (condonation of delay) and IA No. 157070/2026 (exemption from filing C/C).
Parties Involved
Petitioners: Sukanti & Anr.
Respondents: Green India Infra Projects Ltd. & Ors.
Counsel for petitioners: Mr. Anand Shankar Jha (Advocate on Record), Mr. Sachin Mintri, Adv. Mr. Abhilekh Tiwari, Adv. Mr. Shubhank Sharma.
Bench: Hon’ble Mr. Justice Pankaj Mithal, Hon’ble Mr. Justice S.V.N. Bhatti.
Court Master: Sneha Das; Senior Personal Assistant: Nidhi Mathur.
Issues / Allegations / Violations
Petitioners allege that the High Court incorrectly deducted 50 % of the salary towards personal expenses while computing compensation, instead of the statutory 33 % deduction.
Findings & Observations
The Supreme Court recorded the submission of senior counsel for the petitioners; no substantive findings were made at this stage.
Penalties / Settlements / Directions
The Court directed issuance of notice on the Special Leave Petition and on IA No. 157072/2026, with the matter returnable within six weeks.
Corrective Actions & Future Obligations
No specific corrective measures were ordered beyond the issuance of notice; the case remains pending.
Final Ruling & Enforcement
The order is procedural, directing notice and setting a six‑week timeline for the pending application; substantive determination on the compensation deduction is yet to be made.