H.G. Infra Engineering Limited has received a provisional completion certificate for its major infrastructure project in Uttar Pradesh. The disclosure is made pursuant to SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, specifically Regulations 30 and 51.
Project Details
The provisional completion certificate was received on June 05, 2026, issued by Adani Road Transport Limited via letter dated May 30, 2026. The certificate declares the project fit for commencement of commercial operations.
Project Description: Execution of Civil and Associated works on Engineering, Procurement & Construction (EPC) basis of Group II segment of the Ganga Expressway. The specific segment runs from Km. 137+600 (Village Nagla Barah, District Budaun) to Km. 289+300 (Village Ubariya Khurd, District Hardoi) with a design length of 151.700 kilometers.
The project involves construction of an access-controlled six lane expressway (expandable to eight lanes) greenfield expressway from Meerut to Prayagraj "Ganga Expressway" in Uttar Pradesh on DBFOT (Toll) basis.
Contract Financials
- Contract Price: ₹4,970.99 crore
- Appointed Date: November 03, 2022
- Schedule Completion Period: 820 days from the appointed date
- Provisional Completion Date: April 30, 2026
Additional Contract Information
- Awarding Entity: Domestic entity
- Nature of Contract: Engineering, Procurement and Construction (EPC)
- Geographic Scope: Domestic
- Execution Timeline: 820 days from the appointed date
- Contract Size: ₹4,970.99 crore
- Promoter/Promoter Group Interest: Not Applicable
- Related Party Transaction: Not Applicable
The disclosure confirms that the provisional completion was achieved within the scheduled timeframe, with the project being declared fit for commercial operations commencement.