Hindustan Zinc Limited Investor Conference Call Transcript Summary
Trading Symbol: HINDZINC
Event Date: November 16, 2026
Key Announcement Details
- Board Approval: The Board of Directors has approved all projects to increase integrated refined metal capacity from 1.1 MTPA to 2.0 MTPA and silver refining capacity from 800 TPA to 1,500 TPA.
- Total Investment: ₹80,000 crores for the complete integrated expansion plan.
- Project Timeline: Expected commissioning over the next 3-5 years.
- Previous Approvals: Includes earlier approved integrated zinc smelter at Debari and other facilities (₹14,000 crores previously approved).
Capacity Expansion Breakdown
- New Zinc Smelter: 765 KTPA capacity
- New Lead Smelter: 200 KTPA capacity
- Silver Refining: Increase to 1,500 TPA (from current 800 TPA)
- Mining Capacity: Expansion from 18 million tons to 35 million tons
- Final Capacity Post-Expansion:
- Integrated zinc capacity: 1.6 million tons
- Integrated lead capacity: 0.4 million tons
- Silver capacity: 1,500 TPA
Funding Strategy
- The company is currently net cash positive with ₹10,000-15,000 crores
- Project expected to be funded through internal accruals
- No permanent net debt anticipated for the project
- Flexibility to use debt or mix of both depending on market conditions
- AAA-rated investment-grade company
Operational and Financial Guidance
- Cost of Production: Zinc cost excluding royalty expected to remain below $1,000 per ton post-expansion
- IRR Expectations: Mid-teen range returns based on conservative assumptions
- LME Price Assumptions: Conservative assumptions below current levels for project evaluation
- Fixed Cost Optimization: Current fixed costs represent 35% of total cost, expected to benefit from scale
Mining Operations Details
- Grade Assumption: 7% mining grade assumed for future operations
- Ore Consumption: 14.5 tons of ore required per ton of refined metal
- Mine Depth: Some mines will go deeper (up to 1,300 MRL), but most expansion will be horizontal
- Mine Lease Renewals: Key mines (Rampura Agucha, Dariba, Zawar group) have leases expiring in 2030
- Risk Mitigation: Management confident about lease extensions citing first right of refusal and government's pro-mining stance
Regulatory Approvals
- Environment clearance, CTE and CTO required for all projects
- Some approval processes already underway
- Mining capacity increase requires fresh mine plan and environment clearance
- Land acquisition in process for certain auxiliaries
Market Outlook and Demand
- India's zinc demand expected to double in next 5-10 years
- Global zinc demand projected to grow at 1.4% CAGR over next decade
- Tightening mined and refined metal supply globally due to mine closures and project delays
- Company has export strategy if domestic demand doesn't absorb full capacity
Project Phasing
- 60% of capex incurred during construction phase
- Detailed year-wise phasing to be provided later
- FY27 capex guidance already provided and being met
- Basic and detailed engineering phase currently underway
Technology and Efficiency
- Adoption of digitalization and automation to improve processes
- Fumers technology for silver recovery being implemented across operations
- Recent debottlenecking of existing fumers has improved performance
Analyst Q&A Highlights
- Management addressed concerns about mine lease renewals in 2030
- Conservative IRR calculations assume continuing operations
- Capex intensity claimed to be competitive with global benchmarks
- Grade dilution concerns addressed through fixed cost optimization
- Silver production increase supported by RD mine expansion and improved recovery