JSW Energy Limited has disclosed a significant capacity addition under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.

Capacity Addition Details

The company successfully added 1,784 MW of generation capacity since April 2026. This includes:

  • 1,484 MW of renewable capacity
  • 300 MW of inorganic thermal capacity through Maruti Clean Coal & Power Ltd

Renewable Capacity Breakdown (FY27 Additions)

The 1,484 MW of renewable capacity added in FY27 comprises:

  • 624 MW solar projects
  • 108 MW wind projects
  • 601 MW hybrid projects
  • 150 MW hydro projects

Current Portfolio Status

With these additions, the company's total installed capacity now stands at 15,237 MW.

Renewable Portfolio (9,279 MW - 61% of total):

  • Wind: 3,125 MW
  • Solar: 2,457 MW
  • Hybrid: 1,916 MW
  • Hydro: 1,781 MW

Thermal Portfolio: 5,958 MW

Future Capacity Pipeline

The company disclosed the following development pipeline:

  • 15.3 GW under construction
  • 2.0 GW of group captive opportunities under advanced discussions (out of 4.5 GW of signed MoUs)
  • 2.4 GW development pipeline

Strategic Targets

JSW Energy has set the following long-term targets:

  • 30 GW of generation capacity by 2030
  • 40 GWh of energy storage capacity by 2030
  • Carbon neutrality by 2050

Background Information

The company began commercial operations in 2000 with 260 MW capacity and has grown to 15.2 GW. It is part of the USD 25 billion JSW Group with presence in steel, energy, infrastructure, cement, and sports sectors.