JSW Energy Limited has successfully commissioned 1,081 MW of renewable energy capacity since April 2026, increasing its total installed capacity to 14,535 MW. The capacity addition comprises:

  • 442 MW of solar power projects
  • 108 MW of wind power projects
  • 381 MW of hybrid power projects
  • 150 MW of hydro power projects

In June 2026, the Company commissioned its wind blade manufacturing facility at Halol, Gujarat. The facility has an annual manufacturing capacity of 450 blades, sufficient to support approximately 600 MW of wind power installations per annum.

With this addition, renewable energy now constitutes 61% of the Company's total installed capacity, comprising:

  • 3,764 MW of wind
  • 2,500 MW of solar
  • 832 MW of hybrid
  • 1,781 MW of hydro assets

The Company's thermal portfolio stands at 5,658 MW.

JSW Energy has a total locked-in generation capacity of 32.1 GW, comprising:

  • 14.53 GW operational capacity
  • 13.0 GW under construction across thermal, hydro, and renewables
  • 4.6 GW pipeline capacity

The Company remains on track to achieve its FY2027 renewable capacity addition target of 3 GW, having already commissioned about one-third of this target to date. This represents nearly 87% of the total greenfield capacity added in all of FY2026.

Future Targets

The company aims to:

  • Reach 30 GW of generation capacity by 2030
  • Achieve 40 GWh of energy storage capacity by 2030
  • Achieve carbon neutrality by 2050

Energy Storage Capacity

The company has 29.6 GWh of locked-in energy storage capacity through:

  • 26.4 GWh from hydro pumped storage projects
  • 3.2 GWh from battery energy storage system