Key Developments

JSW Energy Limited has received the certified copy of the order from the Hon'ble National Company Law Tribunal, Mumbai Bench (NCLT) sanctioning the Scheme of Arrangement between GE Power India Limited (GEPIL) and JSW Energy Limited and their respective shareholders. The order was sanctioned under Sections 230 to 232 and other applicable provisions of the Companies Act, 2013.

Chronology of Events

  • October 1, 2026: NCLT Mumbai Bench issued the Sanction Order approving the scheme
  • October 1, 2026: Company initially informed stock exchanges about the NCLT sanction
  • October 13, 2026: Company received certified copy of the Sanction Order
  • October 14, 2026: Current disclosure made to stock exchanges

Document Availability

The certified copy of the Sanction Order is available on the company's website at https://www.jswenergy.in/investors/scheme-of-arrangement

Next Steps

The Company will intimate the Effective Date and the Record Date for the scheme implementation to the stock exchanges in due course.