Juniper Green Energy Limited has commissioned 35 MW of wind power capacity on September 10, 2026. This capacity forms part of the company's larger 150 MW Wind Solar Hybrid Power Project located at the project site.
The commissioning was witnessed and confirmed by officials from two entities: Gujarat Energy Development Agency and Paschim Gujarat Vij Company Limited. A formal certificate for this commissioning is expected to be issued shortly.
With this new commissioning, the company's capacity under this specific project now stands at 175 MWp out of a total planned capacity of 190 MWp for the project.
As a result of this capacity addition, the aggregate operational capacity of Juniper Green Energy Limited and its subsidiaries now stands at approximately 2,639 MWp of power generation capacity and approximately 500 MWh of Battery Energy Storage System (BESS) capacity as of September 10, 2026.
The disclosure is made pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.