KHOORSURAT LIMITED

Khoobsurat Limited provided a regulatory update under Regulation 30 regarding the progress of its brewery project. The company has received several key approvals and completed critical infrastructure requirements.

Project Approvals Obtained:

  • Received completion order for plots SA 22 & 23 from GIDC (Gujarat Industrial Development Corporation)
  • Obtained NOC approval from the Inspectorate of Factories and Boilers
  • Obtained NOC from the Directorate of Fire and Emergency Services

Pending Approvals:

  • Occupancy Certificate for Plot SA 22 & 23 is under process and expected to be received within the next 15 days
  • NOC from The Pollution Control Board to operate the ETP plant is expected to be obtained by September 25, 2026 (company already has consent to establish the ETP)

Infrastructure Completion:

  • Installation and commissioning of 315 KVA transformer has been successfully completed, which will cater to the energy requirements of the entire factory

Next Steps:

  • All obtained permissions need to be submitted to the Excise Department to obtain permission to operate the plant on a commercial basis
  • The company has already obtained the License to establish a brewery plant

Financial Impact: Financial impact not quantified in the disclosure.