Khoobsurat Limited provided a regulatory update under Regulation 30 regarding the progress of its brewery project. The company has received several key approvals and completed critical infrastructure requirements.
Project Approvals Obtained:
- Received completion order for plots SA 22 & 23 from GIDC (Gujarat Industrial Development Corporation)
- Obtained NOC approval from the Inspectorate of Factories and Boilers
- Obtained NOC from the Directorate of Fire and Emergency Services
Pending Approvals:
- Occupancy Certificate for Plot SA 22 & 23 is under process and expected to be received within the next 15 days
- NOC from The Pollution Control Board to operate the ETP plant is expected to be obtained by September 25, 2026 (company already has consent to establish the ETP)
Infrastructure Completion:
- Installation and commissioning of 315 KVA transformer has been successfully completed, which will cater to the energy requirements of the entire factory
Next Steps:
- All obtained permissions need to be submitted to the Excise Department to obtain permission to operate the plant on a commercial basis
- The company has already obtained the License to establish a brewery plant
Financial Impact: Financial impact not quantified in the disclosure.