Date: 10.08.2026
Board Meeting Outcomes
The Board of Directors of K.P.R. Mill Limited, in its meeting held on 10th August 2026, approved a comprehensive capacity expansion and modernization plan across the Textile Value Chain with a total investment of ₹1,225 Crores.
Expansion & Modernization Projects
Green Field Projects
- New Ready Made Garment manufacturing facility in ODISHA with a capacity of 45 Million garments per annum
- Investment: ₹450 Crores
- Expected Completion: 1st Quarter of 2027-28 [Q1 FY2028]
- New Processing factory at Perundurai, Coimbatore with processing capacity of 10,000 MT per annum
- Investment: ₹250 Crores
- Expected Completion: 2nd Quarter of 2027-28 [Q2 FY2028]
- New Sweater Manufacturing factory in Karumathampatti, Coimbatore with capacity of 2.5 Million Garments per annum
- Investment: ₹75 Crores
- Expected Completion: 4th Quarter of 2026-27 [Q4 FY2027]
Modernization cum Expansion Projects
- Modernization cum expansion of Knitted fabric facility in Arasur, Coimbatore with capacity to produce 15,000 MT per annum
- Investment: ₹90 Crores
- Expected Completion: 3rd Quarter of 2026-27 [Q3 FY2027]
- Modernization cum expansion of Knitted fabric facility in Neelambur, Coimbatore with capacity to produce 20,000 MT per annum
- Investment: ₹100 Crores
- Expected Completion: 4th Quarter of 2026-27 [Q4 FY2027]
- Modernization cum Expansion Spinning Mill unit 3 at Karumathampatti, Coimbatore
- Investment: ₹85 Crores
- Expected Completion: 3rd Quarter of 2026-27 [Q3 FY2027]
- Modernization cum Expansion Spinning Mill unit 1 at Karumathampatti, Coimbatore
- Investment: ₹175 Crores
- Expected Completion: 4th Quarter of 2026-27 [Q4 FY2027]
Key Financial Details
- Total Investment: ₹1,225 Crores
- Expected Turnover from Projects: Approximately ₹2,000 Crores
- Funding: Entire capex will be met through internal accruals