Contract Awards Disclosure

Contract 1:

  • Work Description: Civil Works of 400kV Main Pooling GIS Substation at Kutch, Gujarat under Kutch RE Project Z2
  • Basic Order Value: ₹58.53 Crore (exclusive of GST)
  • Execution Timeline: 9 months from September 25, 2026
  • Mobilization Period: 15 days from date of LOC
  • Nature: Domestic work awarded by domestic entity

Contract 2:

  • Work Description: Civil Works of 400kV Mobile GIS 1 Substation at Kutch, Gujarat under Kutch RE Project Z2
  • Basic Order Value: ₹11.82 Crore (exclusive of GST)
  • Execution Timeline: 4 months from September 25, 2026
  • Mobilization Period: 10 days from date of LOC
  • Nature: Domestic work awarded by domestic entity

Total Contract Value: ₹70.35 Crore (exclusive of GST)

Significant Terms:

  • The company is authorized to proceed with the jobs
  • Other terms and conditions shall be as per mutually agreed General Conditions of Contract (GCC) and Special Conditions of Contract (SCC)/formal Contract

Related Party Considerations:

  • Promoter/promoter group/group companies have no interest in Reliance Industries Limited
  • The contracts do not fall within related party transactions