LCC Projects Limited has received a Letter of Commitment (LOC) from Reliance Industries Limited for civil works related to a 400kV Load Pooling GIS Substation at Jamnagar, Gujarat, under the Kutch RE Project - Z2.

Key Contract Details

  • Contracting Entity: Reliance Industries Limited
  • Project Description: Civil Works for 400kV Load Pooling GIS Substation at Jamnagar, Gujarat under Kutch RE Project - Z2
  • Basic Order Value: ₹62.32 Crore (exclusive of GST)
  • GST Treatment: 18% extra applicable on basic order value
  • Execution Timeline: 9 months from the date of Letter of Commitment (October 9, 2026)
  • Nature of Work: Domestic entity, domestic work
  • Contract Status: Letter of Commitment received, authorizing the company to proceed with the job

Significant Terms and Conditions

  • The company is authorized to proceed with the job based on the Letter of Commitment.
  • Other terms and conditions shall be as per mutually agreed General Conditions of Contract (GCC) and Special Conditions of Contract (SCC).

Related Party Considerations

  • No promoter/promoter group/group companies have any interest in Reliance Industries Limited
  • The contract does not fall within related party transactions

Company Undertaking

The company has undertaken to update the exchanges in case of any further developments in relation to this project.