Date: July 04, 2026

Board Meeting Outcomes

The Board of Directors meeting was held on July 04, 2026, commencing at 04:00 p.m. IST and concluding at 04:40 p.m. IST. The Board approved the proposed capacity expansion of manufacturing capacities of Vertical A of the Company at Dankuni, West Bengal.

Capacity Expansion Details

Project Location: Dankuni, West Bengal

Project Cost: Total ₹600 crores, which includes:

  • Land value acquired in previous years
  • New capital expenditure of approximately ₹450 crores

Capacity Details:

  • Existing capacity utilization: Approximately 80%
  • Proposed capacity addition: Approximately 18-20 crores pieces
  • Manufacturing space addition: 12 lakh square feet
  • Total built-up footprint after expansion: Approximately 20 lakh square feet

Financial Projections:

  • Expected incremental annual revenue: ₹900 crores to ₹1,000 crores
  • Payback period: Approximately 5 years
  • Completion timeline: Approximately 6 years in phased manner

Employment Impact:

  • Direct employment: Approximately 3,000 jobs
  • Indirect employment: Approximately 6,000 jobs

Financing Mode: Internal accruals and debt

Strategic Rationale: Capacity expansion to cater to the Company's growth plans and address increasing future demand. Upon completion, the expanded facility is expected to become one of Asia's largest garment manufacturing facilities.