Work Order Details
Maruti Global Industries Limited received a Sub-Contract Work Order from Naandi Infratech Private Limited (Principal business place: SY NO 66 67, 2ND FLOOR, PLOT NO 26, GREENMARK DEVELOPERS PVT LTD, Madhapur, JUBILEE ENCLAVE, Hyderabad, Rangareddy, Telangana, 500081; GSTN State Code: 36; CIN: U45200AP2009PTC065578).
Work Order Number: MS/25-26/176
Work Order Date: November 24, 2026
Project: MAYFAIR SUNRISE
Subproject: MAYFAIR SUNRISE
Scope of Work
The work order covers execution of works relating to: Construction of Shuttering & Reinforcement, Concrete, Hacking, Brick Work & Plaster, Scaffolding, Chipping, Water Proofing, Tiles & NMR.
Detailed scope includes:
- Work as mentioned in Annexure-A
- Review of drawings provided by Consultant
- Debris removal and maintaining floor neatness for tiles flooring
- Any other work explicitly required for project completion
- Electrical tools related to work
- Safety measures (helmets, safety belts)
Financial Details
Total contract value: Approximately ₹12.16 Crores (₹12,16,11,925.00)
Itemized breakdown:
- Shuttering & Reinforcement: ₹35/- Per Sft for 26,000 Sft = ₹9,10,000.00
- Concrete: ₹300/- Per Cum for 2,500 Cum = ₹7,50,000.00
- Hacking (Internal & External): ₹1/- Per Sft for 2,40,000 Sft = ₹2,40,000.00
- Brick Work:
- Ground Floor: ₹45,000.00 for 150 units = ₹67,50,000.00
- First Floor: ₹48,300.00 for 150 units = ₹72,45,000.00
- Second Floor: ₹35,000.00 for 150 units = ₹52,50,000.00
- Internal Plaster:
- Ground Floor Part-1: ₹54,850.00 for 150 units = ₹82,27,500.00
- Ground Floor Part-2: ₹7,500.00 for 150 units = ₹11,25,000.00
- First Floor Part-1: ₹55,850.00 for 150 units = ₹83,77,500.00
- First Floor Part-2: ₹8,000.00 for 150 units = ₹12,00,000.00
- Second Floor Part-1: ₹35,740.00 for 150 units = ₹53,61,000.00
- Second Floor Part-2: ₹5,000.00 for 150 units = ₹7,50,000.00
- External Plaster:
- External Plaster-1: ₹1,20,000.00 for 150 units = ₹1,80,00,000.00
- External Plaster-2: ₹25,500.00 for 150 units = ₹38,25,000.00
- External Increased Amount: ₹5,000.00 for 150 units = ₹7,50,000.00
- External Brick work Amount: ₹6,000.00 for 150 units = ₹9,00,000.00
- External Updated Amount: ₹12,600.00 for 150 units = ₹18,00,000.00
- Scaffolding:
- Fixing: ₹2.75/- Per Sft for 7,69,650 Sft = ₹21,16,537.50
- Removing: ₹1.75/- Per Sft for 7,69,650 Sft = ₹13,46,887.50
- Chipping: ₹1100/- Per Day for 2,500 days = ₹27,50,000.00
- Waterproofing: ₹25/- Per Sft for 3,45,000 Sft = ₹86,25,000.00
- Tiles: ₹22.5/- Per Sft = ₹3,09,37,500.00
- Dead Mortor Chipping: ₹12,500/- Per Villa for 350 villas = ₹43,75,000.00
Terms and Conditions
- Domestic contract awarded by domestic entity
- Time period for execution: As per the terms of the Work Order
- Rates include only labour involved in all operations and including taxes
- Quality must meet relevant IS standards and maintain work with plumb and line
- Payment Terms: Payment against RA Bills certified by QC Team & Project Manager within 15 days
- Taxes: GST 18% Extra & TDS Applicable
- Retention: 5% retention in every bill, released after handing over
- Liquidated Damages: 10% penalty if external plastering not completed every 10 days
- Delay due to natural hazards may lead to extension of time with 2 additional grace days
Relationship Disclosure
No promoter/promoter group/group companies have any interest in Naandi Infratech Private Limited. The order does not fall within related party transactions.
Business Context
The receipt of this work order is in the normal course of business of the Company and is expected to contribute positively to its operational performance.