Project Update
The company has revised the expected date of commencement of commercial operations for its new SVP manufacturing facility at Unit No 2, Baroda - Halol Road, Jarod. The project implementation schedule has been extended by approximately 12 months.
Revised Timeline
The expected date of commencement of commercial operations has been revised from December 2026 to December 2027.
Reasons for Delay
The timeline revision is primarily attributable to:
- Evolving regulatory requirements
- Additional technical and compliance measures being undertaken
- Implementation and alignment with revised Schedule M requirements issued by the Ministry of Health and Family Welfare
- Alignment of facility and quality management systems with internationally accepted Good Manufacturing Practices (GMP)
- Additional evaluation, planning and implementation efforts required
Company Commitment
The company remains committed to completing the project and commissioning the facility in a systematic manner. The revised timeline is expected to facilitate proper execution and smooth operationalization of the facility.