Key Quantitative Figures

  • 50 MW solar capacity declared commercial operation (third part capacity)
  • Cumulative solar capacity now stands at 250 MW out of total 300 MW solar component
  • Part of 200 MW Renewable Energy Round The Clock (RTC) project capacity
  • Current commercial capacity of NTPC Green Energy Limited Group: 10,621.40 MW
  • New total installed capacity after addition: 10,671.40 MW (increase of 50 MW)

Entities Involved

  • NTPC Green Energy Limited (disclosing entity)
  • Project Sixteen Renewable Power Private Limited (project developer)
  • ONGC NTPC Green Private Limited (joint venture, parent of Project Sixteen)
  • National Stock Exchange of India Limited
  • BSE Limited

Project Details

  • Location: Rajasthan
  • Project type: 200 MW Renewable Energy Round The Clock (RTC)
  • Solar component: 300 MW total capacity
  • Current status: 250 MW now operational (cumulative)

Capacity Impact

  • Pre-addition group capacity: 10,621.40 MW
  • Post-addition group capacity: 10,671.40 MW
  • Capacity increase: 50 MW (0.47% increase)