Date: 12.09.2026
Operational Update / Commercial Declaration
- Second part capacity of 6.3 MW of Vanki Wind Energy Project declared on commercial operation
- Effective from: 00:00 hours of 13.09.2026
- Project location: Nakhatrana, Kutch, Gujarat
- Project owner: NTPC Renewable Energy Limited (wholly owned subsidiary of NTPC Green Energy Limited)
Capacity Impact
- Current commercial capacity of NTPC Green Energy Limited group: 10,836.56 MW
- New total installed capacity after addition: 10,842.86 MW
- Capacity addition: 6.3 MW
Corporate Offices
- Corporate Office: NTPC Green Energy Limited, NETRA Complex, E-3, Udyog Vihar Ph.-II, Greater Noida, UP-201306