Date: 12.09.2026

Operational Update / Commercial Declaration

  • Second part capacity of 6.3 MW of Vanki Wind Energy Project declared on commercial operation
  • Effective from: 00:00 hours of 13.09.2026
  • Project location: Nakhatrana, Kutch, Gujarat
  • Project owner: NTPC Renewable Energy Limited (wholly owned subsidiary of NTPC Green Energy Limited)

Capacity Impact

  • Current commercial capacity of NTPC Green Energy Limited group: 10,836.56 MW
  • New total installed capacity after addition: 10,842.86 MW
  • Capacity addition: 6.3 MW

Corporate Offices

  • Corporate Office: NTPC Green Energy Limited, NETRA Complex, E-3, Udyog Vihar Ph.-II, Greater Noida, UP-201306