Project Details

NTPC Green Energy Limited declared commercial operation of the fourth part capacity of 66.18 MW at the Kalasar Solar Energy Project located in Bikaner, Rajasthan. This capacity is part of the 650 MW solar component under the 500 MW REMCL RTC Project of NTPC Renewable Energy Limited, which is a wholly owned subsidiary of NTPC Green Energy Limited.

Operational Timeline

The commercial operation declaration is effective from 00:00 hours on October 10, 2026.

Capacity Impact

NTPC Green Energy Limited Group:

  • Current commercial capacity: 11,262.51 MW
  • New installed capacity addition: 66.18 MW
  • Total installed capacity after addition: 11,328.69 MW

NTPC Limited Group:

  • Total installed capacity: 91,572 MW
  • Total commercial capacity: 90,492 MW

Organizational Structure

The disclosure clarifies the corporate hierarchy: NTPC Renewable Energy Limited is a step-down subsidiary of NTPC Limited through NTPC Green Energy Limited (NGEL), which is the direct subsidiary.