Disclosure Overview

NTPC Limited (Scrip Code: 532555, ISIN: INE733E01010) submitted disclosures dated 18th and 19th September 2026 to BSE Limited and National Stock Exchange of India Limited. The disclosures were made by its subsidiary, NTPC Green Energy Limited (NGEL), regarding the declaration of Commercial Operation for projects of NTPC Renewable Energy Limited, a step-down subsidiary.

Project Details and Commercial Operation Dates

Gujarat Solar PV Project, Dahod:

  • Third part capacity of 68.22 MW out of a 200 MW project was declared on commercial operation.
  • Effective date: 23rd July 2026.
  • Certification: Based on certificate dated 17th September 2026 issued by Gujarat Energy Development Agency.

Vanki Wind Energy Project, Nakhatrana, Kutch:

  • Third part capacity of 9.45 MW was declared on commercial operation.
  • Effective date: 00:00 hours of 19th September 2026.

Capacity Impact

NTPC Green Energy Limited Group:

  • Prior commercial capacity: 10,842.86 MW (as of 18th September disclosure).
  • After solar project addition: Installed capacity increased to 10,911.08 MW.
  • After wind project addition: Installed capacity increased to 10,920.53 MW.

NTPC Limited Group:

  • Total installed capacity: 91,164 MW.
  • Total commercial capacity: 90,084 MW.