NTPC Limited has declared commercial operation for the third and final part capacity of its Solar PV Project at Ramagundam, Telangana. The disclosure is made pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.
The final part capacity of 41.6 MW out of the total 176 MW project has been declared on commercial operation with effect from 30th June 2026. This follows the earlier commissioning of the first two parts: 100 MW capacity declared on commercial operation with effect from 2nd May 2026, and 34.4 MW capacity declared on commercial operation with effect from 29th May 2026.
With the commissioning of this final 41.6 MW capacity, the full project capacity of 176 MW at Ramagundam is now declared commercially operational.
This addition brings NTPC group's total installed capacity to 90,899 MW and commercial capacity to 89,819 MW.