Nature of the Event
Disclosure under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015 regarding declaration of Commercial Operation Date (COD) for a solar power project.
Key Quantitative Figures
- Project Capacity: 105 MW (eighth and last part of 1200 MW Khavda-II Solar PV Project)
- NTPC Green Energy Limited Group commercial capacity: 10,516.40 MW
- NTPC Green Energy Limited Group installed capacity after addition: 10,621.40 MW
- NTPC Limited group total installed capacity: 90,773 MW
- NTPC Limited group commercial capacity: 88,893 MW
Dates of Action
- Disclosure Date: 27th May 2026
- Commercial Operation Effective: 28th May 2026 at 00:00 hrs
Parties Involved
- Disclosing Entity: NTPC Green Energy Limited (NGEL), a subsidiary of NTPC Limited
- Project Owner: NTPC Renewable Energy Limited, a wholly owned subsidiary of NTPC Green Energy Limited
- Project Location: Gujarat, India
- Regulatory References: SEBI Listing Regulations 30
Capacity Impact
The declaration of commercial operation for the 105 MW capacity represents the completion of the 1200 MW Khavda-II Solar PV Project. This addition increases NTPC Green Energy Limited Group's installed capacity by 105 MW from 10,516.40 MW to 10,621.40 MW.