Date: September 30, 2026
Board Meeting Outcomes
- Clarion Wind Farm Private Limited, a step-down subsidiary of Orient Green Power Company Limited, held a meeting of its Investment Borrowing and Banking Committee of Board of Directors on September 30, 2026
- The committee reviewed the progress of the repowering of 7.8 MW Wind Energy Generators
- Approved revision of the completion timeline to November 30, 2026 (subject to approval from statutory authorities)
- The previous committed date was September 30, 2026, as intimated by the company on July 22, 2026
Other Operational / Legal / Strategic Disclosures
- The repowering project involves 7.8 MW of wind energy generation capacity
- The timeline extension is contingent upon receiving necessary statutory approvals
- The disclosure is made under Regulation 30 of SEBI Listing Regulations