PNC Infratech Limited has disclosed that its subsidiary, Kanpur Lucknow Expressway Private Limited (the Concessionaire), has received a Provisional Completion Certificate (PCC/PCOD) for a Hybrid Annuity Mode (HAM) project. The certificate was issued by the Independent Engineer via email dated June 11, 2026, and declares the project fit for entry into commercial operations effective from April 27, 2026.

Project Details

  • Authority: National Highways Authority of India (NHAI)
  • Project Mode: Hybrid Annuity Mode (HAM)
  • Nature of Contract: Construction of Six lane upgradable to Eight lane of Kanpur Lucknow Expressway including spur from km.10.980 to km.28.500 in the state of Uttar Pradesh under Bharatmala Pariyojana (Package-I)
  • Appointed Date: February 1, 2023
  • Completion Period: 910 Days
  • Revised Scheduled Completion Date: April 27, 2026
  • Provisional Completion Date: April 27, 2026
  • Bid Project Cost: ₹1,413.0 Crores (plus Price Index Multiple amount as per the Concession Agreement)
  • Amendments/Terminations: Not Applicable (NA)