Disclosure Context
Rajputana Stainless Limited (Scrip Code: 544731, Symbol: RSL) submitted a regulatory disclosure to BSE Limited and National Stock Exchange of India Limited on September 7, 2026. The disclosure is made under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, read with SEBI Master Circulars SEBI/HO/CFD/PoD2/CIR/P/0155 dated November 11, 2024 and SEBI/HO/CFD/PoD2/CIR/P/2024/185 dated December 31, 2024.
Board Meeting Details
The Company's board meeting was held on September 7, 2026, commencing at 4:00 p.m. and concluding at 5:40 p.m. During this meeting, the board approved the awarding of two renewable energy contracts.
Wind Power Project Contract
- Contract Awarded To: Suzlon Energy Limited, Ahmedabad
- Project Capacity: 2.10 MW (AC) Wind Power Project
- Location: Jamjodhpur site, Gujarat
- Technical Specifications: 1 No. of Suzlon make S1201402100kW capacity Wind Turbine Generator
- Execution Timeline: 11 months
- Contract Value: INR 1,621 Lacs + GST per WTG
- Nature: Domestic project awarded by domestic entity
- Related Party Status: No promoter/promoter group/group company interest; not a related party transaction
Solar Power Project Contract
- Contract Awarded To: Prozeal Green Energy Ltd, Ahmedabad
- Project Capacity: 8.00 MWp (DC) capacity Solar PV Ground Mounted
- Location: Banaskatha site, Gujarat
- Execution Timeline: 4 months
- Contract Value: INR 22.71 Crores + GST per WTG
- Nature: Domestic project awarded by domestic entity
- Related Party Status: No promoter/promoter group/group company interest; not a related party transaction
Project Purpose
Both renewable energy projects will cater to the captive power needs of Rajputana Stainless Limited, providing dedicated power supply for the company's operations.
Compliance & Signatory
The disclosure was signed by Richa Sanjeev Prashar, Company Secretary & Compliance Officer of Rajputana Stainless Limited, and includes the required annexures as per SEBI LODR regulations.