Date: 29 September 2026
Capacity Expansion Update
The company has completed de-bottlenecking activities at its Jayanthipuram works, NTR District, Andhra Pradesh, resulting in significant capacity increases:
Clinker Capacity:
- Increased from 4.61 Million Tonnes per Annum (MTPA) to 5.62 MTPA
- Capacity addition: 1.01 MTPA
- FY26 capacity utilization: 84%
Cement Grinding Capacity:
- Increased from 3.65 MTPA to 4.38 MTPA
- Capacity addition: 0.73 MTPA
- FY26 capacity utilization: 57%
Aggregate Company Capacity:
- Total clinkerisation capacity: 16.95 MTPA
- Total cement grinding capacity: 27.17 MTPA
Project Details:
- Period of capacity addition: Already completed (as of 29 September 2026)
- Investment required: Described as "de-bottlenecking" (no specific amount disclosed)
- Mode of financing: Not specified
- Rationale: Not specified
Not Specified Sections
No material disclosures under the following sections:
- KMP / Board / Auditor Changes
- Dividend Declaration or Non-Declaration
- Board Meeting Outcomes
- Financial Results
- Auditor's Report
- Disinvestment / Strategic Actions
- Media Release / Investor Communication
- Other Operational / Legal / Strategic Disclosures
Analytical Impact: #StrategicExpansion