Project Status Update
The project is in its final stages of completion with the following specific progress details:
- Civil construction has been completed
- Interior finishing works are nearing completion
- Installation and commissioning of building systems are nearing completion
- Furniture installation is nearing completion
- Landscaping works are nearing completion
Operational Timeline and Approvals
The Company expects the resort to commence operations in the coming months, subject to:
- Completion of the remaining works
- Receipt of requisite statutory approvals
Project Specifications and Significance
- Project designation: Prestigious Rising Rajasthan MoU Project
- Location: Pushkar
- Scale: Will be the largest hotel in both Pushkar and Ajmer upon opening
- Capacity: 177 rooms
- Land reserves: Significant land reserves available for future expansion
Future Business Plans
The Company expects to host its first wedding events during the upcoming 2026 winter wedding season.
Documentation
Recent project photographs were enclosed with the submission to highlight the current stage of development at the project site.
Authorization
The disclosure was signed by Girdhar Saboo, Managing Director of Spectrum Foods Limited, on 13/07/2026 at 14:43:51 +05'30'.